Field Observation, Handover and Sign-Off

Someone signed off on this.
Here's the 2-minute check that would have stopped it.

Before you sign off a network install, open the comms enclosure and check three things: nothing is inside that wasn't installed, you can tell what every cable is for without asking, and every loop is tied and dressed. It takes 2 minutes. Any "no" means the job isn't finished, so hold the sign-off until it is.

2 minTo run the check
3Yes or no questions
1,000+Sites we've taken over and taken live
350Enclosures dressed and labelled
Open nbn enclosure after handover with orange leads knotted in the bottom, packaging left behind, no labels and conduit through a rough hole in the top.

Actual field photograph, taken when we arrived to take the site live. Site details withheld.

The installer packed up, the job was accepted and the invoice was paid. Nothing was broken, so it passed. That's the lowest bar a handover can set, and it's the one most of them use.


It passed because nothing was broken.

Then someone opened the door. Orange leads knotted in the bottom of the enclosure. Packaging and offcuts bagged and left behind. No labels anywhere. Conduit pushed through a rough hole in the top.

Found
Leads knotted in the bottom
Spare length dumped on the floor of the enclosure instead of coiled, tied and fixed off.
Found
Packaging left behind
Offcuts and bags stored in the enclosure. It isn't storage.
Found
No labels anywhere
The next technician has to trace every lead by hand before they can start on the fault.
The handover test
Does it work?
Yes. So it was signed off. Nobody asked whether it was finished.

Most handovers ask one question: does it work? Working proves the service is up today. It says nothing about whether the next technician finds a fault in minutes or spends hours tracing unlabelled leads first.

Testing still matters, and it's a separate step. We cover it in network acceptance testing. This check is the bar above it: is the job finished?

Three questions at the open door, before you sign.

Stand at the open enclosure with the installer still on site. Answer each one yes or no.

  1. Is there anything in there that isn't installed? Packaging, offcuts, spare leads, a bag of bits. Loose material blocks airflow and hides what's actually connected.
  2. Can you tell what every cable is for without asking? A label at both ends that matches the port schedule. If you have to ring the installer to find out, so will everyone after you.
  3. Is every loop tied and dressed? Spare length coiled, tied and fixed off. Not knotted on the floor of the enclosure.
Any "no" and the job isn't finished

Say so before you sign, while the installer is still on site. The list is short on purpose. If a check takes longer than 2 minutes, it won't happen at handover.

Signing off sites you'll never visit?

Make the photo the deliverable. No photo of the finished, open enclosure, no sign-off and no final payment. It takes the installer 30 seconds, and you can check 50 sites from your desk. Who should hold that record afterwards is covered in who owns the risk in that cabinet.

"Fixing it while the installer is on site costs them 20 minutes. Finding it later costs you a callout."

20 minutes now, or a callout later.

Before handover, clearing out the enclosure, labelling the leads and tying off the loops takes the installer about 20 minutes. After handover, it's a new job on your budget.

01
Every fault starts with tracing
Unlabelled leads mean the first part of every callout is working out what's what. You pay for that time on every visit, not once.
02
The fix becomes a separate job
Once the job is accepted and paid, the installer has no reason to come back. The tidy-up that was 20 minutes on the day now needs a booking, a visit and a budget.
03
It's not rare
On at least 4 in 10 jobs we're called into, we find installation gaps that need some rework. Across 34 years we've taken over and taken live more than 1,000 sites someone else installed, and dressed and labelled 350 enclosures.

Cheapest on the quote and cheapest over the life of the site are rarely the same job. If 20 minutes for tidy-up was never in the price, it won't be in the box either.

Design, budget, install and sign-off all had a chance. None took it.

The thread under this photo didn't blame the installer. It pointed at every decision before the installer arrived, and at the inspection that never happened after.

LinkedIn thread: original post, 27,798 impressions · 43 reactions · 36 comments
IS
Ian Stanley Director, Ian Stanley Electrical Power Solutions cc

It's easy to blame the person doing the job, but many problems start long before installation, with poor design, procurement, planning and management. ... If we want better workmanship, we need to look beyond the person holding the tools and start questioning the decisions that put them in that position. Accountability starts at the top, too.

DB
David Barrett AAA Communications, Author

Fair call, Ian, and that's exactly why the post is aimed at whoever signs off, not whoever holds the tools. The person who set the budget and the deadline is usually the same person accepting the job. If 20 minutes for tidy-up was never in the price, it won't be in the box either.

KO
Karl O'Regan Head of Engineering Solutions, Integrated Media Solutions IMS

If this is in the context of an MDU deployment, having a pre-installation mock up design agreed by all parties and installed onsite ensures the standard has been set from the outset. Any deviations from that should be picked up by independent onsite audits.

DB
David Barrett AAA Communications, Author

That's the right order, Karl. The mock-up sets the standard everyone signs up to, and the independent audit checks it was actually met. Without the second step, the mock-up is just a nice photo.

TR
Thomas Richard Member I.B.E.W. Local 134

What needs to start to happen is a physical inspection installer and customer to visually check and make sure everything is installed correctly.

DB
David Barrett AAA Communications, Author

Exactly, Thomas. Installer and customer standing at the open door together for 2 minutes before anyone signs. It's the cheapest inspection there is, and it's the one that gets skipped most.

PM
Former IT project manager Commenter on the original post

I used to run IT projects for the likes of easyJet and John Lewis so you can never look at the detail like this. Hence you have to hope that people have some ethics and want to do a job properly.

DB
David Barrett AAA Communications, Author

At that scale you can't open every box, so don't rely on ethics. Make the photo the deliverable. No photo of the finished enclosure, no sign-off and no final payment. It takes the installer 30 seconds and you can check 50 sites from your desk.

36 comments. One pattern.

Electrical contractors, engineers and project managers, all describing the same gap between "it works" and "it's finished".

The worst handover
"Once we were asked to diagnose why none of the LAN ports on the wall were working..." Every cable had been cut at the patch panel and again at the ceiling. The fix: trace them all back 10ft and reposition the cabinet before patching.
A shortcut, not a route
"If you look at the orange multimode cable, it just passes through an existing box." A box used as a shortcut rather than a planned route.
No real handover
"Most sites have been handed over without a proper handover process, either because the people responsible have already wrapped up their work or because they lack the necessary knowledge and understanding to ensure a smooth handover."

We open every enclosure before you sign. Or after, if it's too late.

We didn't install the enclosure in the photo. On jobs like this, clients bring us in afterwards to take the site live: plug in and set up the equipment, work with the carrier until the service is up, and run user acceptance testing with the staff. Every enclosure gets a before and after photo in the handover pack.

Technician visit A$495 ex GST
  • Up to 90 minutes on site
  • The 3-question check on every enclosure, with before and after photos
  • The 20-minute tidy included: clear it out, label the leads, tie and dress the loops
  • Site report within 24 hours: photos, findings, the fixes made on the day, and each further item with a photo and description
  • Bigger than 20 minutes, or needs parts? A fixed-cost quote within 48 hours, and we come back to finish. Nothing extra without your approval.

Appointment confirmed within 1 business day. Over 1,000 sites taken over and taken live in 34 years.

Book a technician visit, A$495 ex GST

Not ready yet? Send 3 photos. Get a free cabinet review. Rate My Rack

If the whole cabinet needs rebuilding rather than tidying, Cabinet Reset is a fixed-scope package for one small cabinet: labelled, tested, port schedule and handover photos, A$1,500 to A$3,000 ex GST. For a whole site, start with a Layer 1 Network Audit.

AAA Communications is a Sydney-based network infrastructure contractor. Since 1992 we've installed, tested and documented commercial data cabling and Wi-Fi on live office, branch, retail and industrial sites nationally: 34 years on live networks.

What does your handover sign-off actually check?

The rest of the handover.

Network install sign-off, explained.

What should I check before signing off a network installation?
Open the comms enclosure and check three things: nothing is inside that wasn't installed, every cable can be identified without asking, and every loop is tied and dressed. It takes 2 minutes. Any "no" means the job isn't finished, so hold the sign-off until it is.
Isn't testing enough?
No. Testing proves the network works today. The enclosure shows whether the next technician can find a fault quickly or has to trace unlabelled leads first. Do both: test it, then check it's finished.
Who is responsible for a messy enclosure after handover?
In practice, whoever accepted it. Once the job is signed off and paid, fixing it is a new job on your budget. That's why the check happens before you sign, while the installer is still on site.
Can you take over a site someone else installed?
Yes. We've taken over and taken live more than 1,000 sites someone else installed. We plug in and set up the equipment, work with the carrier until the service is up, run user acceptance testing with your staff, and dress and label the enclosure, with before and after photos in the handover pack.
How long does it take to fix an untidy enclosure?
About 20 minutes if the installer fixes it before leaving. After handover, our technician visit is A$495 ex GST for up to 90 minutes on site, and that includes the 20-minute tidy. If it needs longer or parts, you get a fixed-cost quote within 48 hours, and we come back to finish.
What do I get at the end of the technician visit?
A site report within 24 hours: photos, the technician's findings, the simple fixes made on the day, and a line item with a photo and description for any further work. Any follow-on work is quoted within 48 hours, and nothing extra is done without your approval.
Before your next project

Get the checklist we run before every remediation quote.

It is the same set of questions that turns a surprise blowout into a known cost, on the page before work starts. Put your email in and we will send it to you.

One email with the checklist. No spam, unsubscribe anytime.

Ready now? Book a technician visit, A$495 ex GST.

Already signed off?

Up to 90 minutes on site, the 20-minute tidy included, and a site report within 24 hours. A$495 ex GST, appointment confirmed within 1 business day.

Book a technician visit